| Remarks | Planned maintenance activities at exit point AGRS Sevlievo and AGRS Lovech.
100 % unavailability of the affected assets for the period 11.08.2026, 7:00 EET – 14.08.2026, 7:00 EET, due to tie-in works for new facilities and pipeline section relocation related to Hemus Highway construction. Available capacity of the affected assets (exit points) during the event: 0 kWh/d - AGRS Sevlievo C040P01 - 58ZC040P01SEVL-9, AGRS Sevlievo C040P02 - 58ZC040P02SEVL-2, AGRS Lovech C039P01 - 58ZC039P01LOVC-N, AGRS Lovech C039P02 - 58ZC039P02LOVC-G, AGRS Lovech C039P03 - 58ZC039P03LOVC-9, AGRS Lovech C039P04 - 58ZC039P04LOVC-2.
Estimated duration of the unavailability: 72h |